Why Does the DOE Want Such Detailed Submittals?

It’s a common question among contractors: Why does the Department of Energy (DOE) require such detailed submittals for their projects? Understanding the reasons behind these stringent requirements can help contractors better prepare and navigate the submittal process.

The DOE’s Responsibility

The DOE manages a vast array of large industrial and nuclear facilities, as well as research facilities for the government. Given the critical nature of these facilities, the DOE has a high level of responsibility to ensure that all projects meet stringent safety and operational standards. Detailed submittals are a part of this rigorous oversight.

Historical Context of Detailed Submittals

The DOE’s insistence on detailed submittals stems from past experiences where less detailed oversight led to significant issues. When contractors were left to their own devices without strict scrutiny, there were instances where:

  • The wrong equipment was installed.
  • Equipment was installed incorrectly, leading to fit-up issues and collisions with other components.

To avoid repeating these costly and potentially dangerous mistakes, the DOE now requires very detailed submittals, almost to the point of being engineering-level documents. This ensures every aspect of the installation is scrutinized and validated before work begins.

The Role of Detailed Drawings and Engineering Documents

For the DOE, detailed drawings and engineering documents are critical. When contractors submit detailed submittals, the DOE can:

  • Ensure that all components will fit correctly and function as intended.
  • Identify potential issues before they become problems in the field.
  • Validate that all installations meet seismic, safety, and operational standards.

This level of detail might seem over the top, but it is necessary for maintaining the high standards required for DOE facilities, especially those involving nuclear and other sensitive operations.

The Installer’s Perspective

From the installer’s point of view, these detailed requirements can seem burdensome. Installers might wonder why they are responsible for generating detailed engineering drawings when they are only there to install the equipment. The expectation is that the installer will provide:

  • Detailed submittals including full engineering drawings.
  • Bills of material with all components specified.
  • Load calculations and other necessary engineering validations.

The DOE expects these detailed submittals because they often do not pay for upfront engineering services to this level of detail. Instead, they rely on the contractor to provide this information as part of their submittal process. This approach can be particularly challenging for contractors who are used to working with simpler, less detailed submittals.

Managing Complexity and Ensuring Compliance

For smaller systems like HVAC, potable water, or fire systems, the DOE still requires these detailed submittals to ensure compliance with their standards. This can lead to submittal packages that are hundreds of pages long, covering every aspect from seismic requirements to detailed drawings of each component.

The Importance of Coordination

Contractors need to understand that their submittals are part of a larger puzzle. The DOE’s review process involves multiple stakeholders, including:

  • General contractors
  • Electrical and mechanical installers
  • The DOE’s own quality review and technical management teams

Each of these groups will review the submittals to ensure that all components work together seamlessly. This level of coordination helps prevent issues that could arise from one team not being aware of what another is doing.

Conclusion

In a perfect world, the DOE would provide a 100% design package, complete with all necessary drawings, bills of material, and load calculations. However, this is rarely the case. The responsibility often falls on the installer to provide detailed submittals that meet the DOE’s high standards.

Contractors bidding on DOE projects need to be prepared for this rigorous process. Understanding why the DOE requires such detailed submittals can help contractors better prepare their packages, avoid rejections, and successfully complete their projects.

Related posts