Baghouse Study
Project Summary
JBW Consulting Engineers conducted a study on Baghouse #2, which was not operating as desired, with the frequency of bag replacements remaining high despite the installation of the FCOS cyclone. The client requested JBW to perform a comprehensive analysis of the baghouse system. The scope of work included a site visit to obtain air test readings across the system and gather operational data from the field and personnel. JBW then developed a report summarizing the findings and provided recommendations for improving the baghouse's performance based on the information collected and their expertise with similar systems.
Services Provided
Mechanical Engineering
Pipe Stress Analysis
BIM Coordination